Calculating the HZB in advance with many automatic functions can lead to delayed responses
Problem
In the event of an error, a loop in which all automatic functions are processed once takes more than 2 seconds. If the calculation is missed for the sector where a transition from dark and “sun hidden” to bright and “sun visible” occurs, glare occurs because the bright command is issued n minutes too late.
Workaround
The "Shading Lead-in" feature can counteract the delayed response (RM10978).
Occurs in version
- .1.0.1.18
- .1.4.1.18
- 307.1.1.1.18
- 308.1.1.1.18
- 312.1.1.1.19
- 313.1.1.1.19
- 314.1.5.1.19
- 331.1.1.1.20
- 332.1.1.1.20
- 333.1.5.1.20